# LG CNS finishes 30MW AI data centre in Jakarta

> LG CNS has finished a 30MW AI data centre in Jakarta, with its full capacity leased before completion and a next phase designed to reach 400MW.

- Published: 2026-11-02
- Topic: [AI](https://futuretechnologyhq.com/topic/ai/)
- URL: https://futuretechnologyhq.com/article/lg-cns-finishes-30mw-ai-data-centre-in-jakarta/
- Publisher: [Future Technology HQ](https://futuretechnologyhq.com/), free to read. Quote as "Future Technology HQ" with a link to the article.

## Key points

- The Jakarta facility had customers for its full capacity before construction finished, which The Elec says gives LG CNS a stable revenue base from the start of operations
- The power system can handle more than 300kW per rack, about 60 times what a typical data centre rack requires
- LG CNS says it will proceed cautiously on GPU-as-a-Service spending, even though its board has already approved 381.4 billion won for GPUs and infrastructure equipment

## Article

LG CNS has completed a 30-megawatt (MW) hyperscale AI data centre in Jakarta, and customers had secured the facility's full capacity before construction finished. The Korea Times reports it as the first time a Korean company has built an AI data centre overseas for a local client.

The company is already designing a next phase that would take total power capacity to 400MW once complete, which would make it one of Indonesia's largest AI data centre facilities. Set against that, the 30MW first phase reads as a starting point.

## What changed

The facility was commissioned last year by KMG, a joint venture between Indonesia's Sinar Mas Group and Korea Investment Real Asset Management. A completion ceremony took place in Jakarta on Sunday, attended by LG CNS chief executive Hyun Shin-kyoon and Sinar Mas Group chairman Franky Widjaja. LG CNS said on Monday, 2 November 2026, that it had finished construction and had secured customers for the facility's full capacity beforehand.

The Elec's reporting from LG CNS's third-quarter earnings call, held on 30 October, fills in the commercial history. LG CNS signed a data centre consulting and design contract with KMG in 2024, then secured a 100 billion won infrastructure construction contract in August 2025. It took part in the project through LG Sinar Mas Technology Solutions, its joint venture with Sinar Mas Group. Yoo Ki-woong, vice president of LG CNS's AI and Cloud Business Division, said on the call: "We secured customers to lease the entire facility before completion, establishing a stable revenue base from the start of operations."

The first-phase building has 11 above-ground floors, a total floor area of 46,281 square metres and a power intake capacity of 30MW. It can accommodate more than 100,000 servers.

The technical headline is power density. LG CNS installed a power system capable of handling more than 300 kilowatts per rack, about 60 times the power capacity required by a typical data centre rack. The infrastructure uses redundant power systems so that operations continue around the clock, even if the primary power supply is disrupted.

Cooling is hybrid. The first phase uses air cooling, with liquid cooling, where a coolant carries heat away from the chips rather than moving air across them, to be introduced in later phases to support high-density AI server environments. The data centre was designed to support high-performance computing powered by next-generation graphics processing units (GPUs).

The wider LG Group contributed as well. The project features an integrated "One LG" solution: LG CNS provided its design, build and operate (DBO) expertise, LG Electronics supplied air-conditioning systems and LG Energy Solution provided batteries, enabling integrated delivery of power, cooling and energy infrastructure.

## Impact on businesses

The Korea Times says the project marks LG CNS's expansion into overseas markets, leveraging its DBO capabilities. LG Electronics supplied air-conditioning systems and LG Energy Solution supplied batteries within the same integrated package. Hyun said the project demonstrates LG CNS's ability "to bring the expertise we have developed in Korea to overseas customers" and strengthens its competitiveness in the global market.

LG CNS's investment stance on GPUs is described as cautious. Chief financial officer Song Kwang-ryun told the earnings call that he sees medium- to long-term growth potential in GPU-as-a-Service (GPUaaS, renting GPU capacity to customers), and that the company is reviewing opportunities involving LG Group affiliates and external enterprises. He also pointed to the substantial upfront investment costs and the rapid pace of technological change. "We will proceed cautiously, focusing on projects with established commercial viability," Song said of future investments.

That caution sits alongside a commitment already made. At a board meeting on 11 September, LG CNS decided to invest 381.4 billion won in GPUs and infrastructure equipment, including Nvidia's Vera Rubin, with the equipment acquisition scheduled for 30 June 2027. GPUs require substantial upfront capital, and rapid replacement cycles mean customer acquisition and utilisation rates can significantly affect investment returns.

LG CNS has also broadened its domestic portfolio beyond colocation and DBO services to include prefabricated modular data centres, GPU-as-a-Service and liquid-cooling infrastructure. It plans to build on these capabilities to expand its AI factory business, integrating AI platforms and services.

## Impact on consumers and users

Ordinary users are unlikely to notice a single building like this one directly. The facility is designed to host AI computing, and Hyun says demand for AI computing is surging across the Asia-Pacific region, which is one of the regions where LG CNS plans to expand.

## Impact on the wider industry

LG CNS has paired that power capability with a staged approach to cooling: air first, liquid in later phases.

On scale, the Korea Times reports that LG CNS is designing a next phase that would raise the data centre's total power capacity to 400MW. The Elec reports that project owner KMG plans to expand total power intake capacity to 220MW. The sources do not reconcile the two figures, which may refer to different scopes, but both are well above the 30MW first phase.

LG CNS says it plans to expand its AI data centre business across Asia-Pacific, including Malaysia, Thailand, Vietnam, the Philippines and Japan. The Elec adds that the company is pursuing additional data centre construction projects in Indonesia and exploring expansion into North America and Europe. There, LG CNS plans to focus on prefabricated modular data centres. According to the company, the modular approach reduces on-site construction work compared with conventional methods and allows facilities to be expanded in stages according to customer demand. Yoo said LG CNS is pursuing business cooperation through its US subsidiary and local partners, and plans to enter the market using modular data centre technology designed to support Nvidia's next-generation AI platform, Vera Rubin.

For IT leaders weighing resilience as capacity grows, see [backup vs disaster recovery, and BC vs DR plans explained](/article/backup-vs-disaster-recovery-bc-vs-dr/).

## What comes next

Few firm dates have been published, but the sequence is clear from what LG CNS has said.

- **Now:** the 30MW first phase is complete, with customers secured for its full capacity.
- **Coming months:** LG CNS is designing the next phase and is pursuing additional data centre construction projects in Indonesia.
- **30 June 2027:** scheduled equipment acquisition for the GPUs and infrastructure equipment, including Nvidia's Vera Rubin, approved by the board on 11 September.
- **Later phases:** liquid cooling is introduced to support high-density AI server environments.
- **Beyond Indonesia:** Malaysia, Thailand, Vietnam, the Philippines and Japan are named expansion targets in Asia-Pacific, with modular data centres planned for North America and Europe.

LG CNS's third-quarter numbers show how central this area is to the business. AI and cloud revenue reached 961.5 billion won, accounting for 57.8% of total revenue of 1.6643 trillion won.

## Key takeaways

- The Jakarta facility had customers for its full capacity before construction finished.
- Its power system can handle more than 300kW per rack, about 60 times what a typical data centre rack requires.
- LG CNS says it will proceed cautiously on GPU services, separately from the 381.4 billion won in GPU and infrastructure spending its board has already approved.
- Prefabricated modular data centres are the company's stated route into North America and Europe.

## Net assessment

The completed Jakarta facility is a milestone for LG CNS, KMG and the LG affiliates that supplied cooling and battery equipment, and it gives the company a base for its Asia-Pacific plans. The next phase is under design, with 400MW cited by LG CNS and 220MW cited as KMG's expansion plan, and liquid cooling is due in later phases. IT teams interested in dense AI hosting in the region should follow how the next phase develops.

## Sources

- [Korea Times](https://www.koreatimes.co.kr/business/companies/20261102/lg-cns-completes-30-mw-ai-data-center-in-indonesia)
- [The Elec](https://www.thelec.net/news/articleView.html?idxno=15116)
- [Yonhap](https://en.yna.co.kr/view/AEN20261102003900320)